Robina Health Precinct - On Site Progress







Level 1
Plasterboard sheeting to Partition walls
Complete Plumbing rough in

Level  2
Structural steel to Partition walls
Services rough in to Partition walls
Complete external Window glazing

Level 3
Complete High level Services rough in
Erect Partition stud walls

Level 4-Roof
Completing substructure framework
Commence Window sub sill installation
Commence Box gutter/Roof sheeting

External Facade work
Substrate structure East / Northern elevations

Stage 2 Car Park
Soft ground Civil works