Practical Completion at Masters at Nerang





Glenzeil has reached Practical Completion at Masters at Nerang and we have successfully handed the building over to our Client's fit out team. 
The building took approximately ten months to complete and is a total of 14,000 m2 comprising a Trade Area, Large Retail Area, Nursery Area,
McDonalds and Administrative Offices on the second level.  The construction also included a large carpark and landscaping works. 