Tuesday, November 29, 2011

Robina Health Precinct - Project Progress



Background

In late 2009 a Project Team was established and engaged to progress the planning, design and delivery of the Robina Health Precinct.

In consultation with the Gold Coast Health Service District, the Project Team responded to the requirements outlined in the Health Services Plan (inc. Various Addenda) via preparation of the site Master Plan (MP), Schematic Design, Design Development and Contract Documentation.

In November 2010, and in-line with the available funding, the Project Team released Tender Documentation for Stage 1 of development. Glenzeil won the tender and was awarded the contract just prior to Easter 2011 and construction commenced soon after.

Brief Outline of Preferred Option

The Design for Stage 1 of the Robina Health Precinct delivers accommodation for the following service providers:
-          Multidisciplinary Clinic
-          Cardiac Rehabilitation
-          Child Youth Mental Health
-          Child Youth & Family Services
-          Palliative Care & Community Liaison

This accommodation is supported by a range of associated ‘Front of House’ / ‘Shared Facilities’ and ‘building services’.

Progress

Construction of the Robina Health Precinct is progressing with services roughly at 80% complete and internal fit out of 4 levels at 40% complete.

Car parking for the building is being made ready for pavement finishes and is expected to be complete in late January.

The project regularly has a workforce of around 90 - 95 men on site daily.

Monday, November 21, 2011

Lismore Gateway Motel - On Site Progress






On-site Progress:

·         Landscaping commenced
·         Carpet laying - 75 %
·         Painting Internal/External - 75 %
·         Tiling – 95 %
·         Carpentry – 90%
·         Electrical fit-off – 85 %
·         Plumbing fit-off -  85 %
·         Fencing – 50 %


Beenleigh Police Station - On Site Progress





On-site Progress:

- Stage 1, 2 and 3 complete.

- Stage 4 complete week ending 25th November.

- Final completion scheduled for 23rd December.