BLU Villas @ South Bay - Practical Completion










Glenzeil commenced construction of ‘Blu’: 11 x waterfront terrace homes at Varsity Lakes on the Gold Coast on the 16th January 2012. This is the 2nd development for developer Ben Skubris who previously teamed up with Glenzeil to complete the ‘H20’ apartments and villas at Varsity Lakes in 2009/10.

These architecturally designed terrace homes all have living areas connected seamlessly to north facing suspended timber decks, with approx. 200m2 of internal floor area and up to 50m2 of decks and balcony area. Each of the eleven home designs feature three bedrooms, ducted air conditioning and luxury finishes and fittings over two levels.

Environmental considerations include, 3000 litre water tanks, north facing aspect, insulated roofs, heat pump hot water systems, covered outdoor living areas with sunhoods and screens to all west facing windows.

The Certificate of Classification & Practical Completion was achieved on programme on the 19th October 2012.

Congratulations to Matt Sanders, Alan Moss, Matt Skrinis, Jimmy Pearce, Neil Brindley, Lauren Blair, Jason Ford and Kaha Mohi.



Sunday, December 2, 2012

'The Plaza' South Brisbane

November 2012
Welcome to our November newsletter for ‘The Plaza’ South Brisbane. The newsletters are in relation to the progress on site and program updates. Please find enclosed progress photos and reports; key dates; list of subcontractors and suppliers; safety updates and Glenzeil contact details.
 
PROGRESS PHOTOS: Taken 29/11/2012

 
Russell Street Frontage

Rear Corner of Site

PROGRESS REPORT:

Excavation & Earth Retention
·         Clearing of site vegetation nears completion.
·         Raking Piling works nearing completion.
·         Bulk excavation has commenced.
·         Removal of rock and soil is underway.
·         Capping beam approximately ¼ complete.

KEY DATES:
·         Crane Install – 27th March 2013
·         Scaffold Install – 8th June 2013
·         Basement 2 Slab Pour – 29th April 2013
·         Basement 1 Slab Pour – 14th May 2013
·         Ground Level Slab Pour – 27th May 2013
·         Hoist Install – 29th June 2013
·         Install Lift Roof – 1st November 2013
·         Finish Main Roof – 1st November 2013
·         Hoist Removal – 21st February 2014
·         Scaffold Removal – 31st January 2014
·         Crane Remove – 5th February 2014
·         Handover – 27th March 2014
·         Pour 1 First Level Slab – TBA
·         Pour 2 First Level Slab – TBA
·         Pour 1 Second Level Slab – TBA
·         Pour 2 Second Level Slab – TBA
·         Pour 1 Third Level Slab – TBA
·         Pour 2 Third Level Slab – TBA

LIST OF SUBCONTRACTORS & SUPPLIERS:

TRADE           
POSITION
Civil Works
Delta Group
Electrical
CV Services Group
Fire Sprinklers
Select Fire
Lifts
MP Lifts
Mechanical – A/C
Climate Control
Plumbing
Underground Plumbing
Surveyor
Bennett & Bennett
Tower Crane & Hoist
Lindores Constructions Logistics


SAFETY:
  • A site specific Workplace Health and Safety Plan has been produced and is available for inspection.
  • There have been 0 No. incidents to date
  • No visits to site from Queensland Workplace Health & Safety to date.
GLENZEIL SITE STAFF:
 
NAME            
POSITION
TELEPHONE
Alan Moss
Operations Manager
5555 3333
Andy Ingram
Project Manager
5555 3333
Joel Martin
Contracts Administrator
5555 3333
Jimmy Pearce
Project Manager
5555 3333
Neil Brindley
Finishing Foreman
5555 3333
Sarah Eke
Administrators Assistant
5555 3333

If you have any items you would like us to include in future issues of the newsletter, please contact Sarah Eke