Tuesday, October 25, 2011

Glenzeil actively supports Safe Work Australia Week 2011


Glenzeil Pty Ltd, one of Queensland’s leading commercial construction companies, is proudly supporting Safe Work Australia Week 2011.

Glenzeil undertook safety activities across its construction sites in Queensland and NSW this week, supporting the campaign of ‘be on a winning team, achieve zero harm at work’. Approximately 100 Queenslanders die each year as a, result of work-related injuries and nearly 30 000 are seriously injured. Safe Work Week is an opportunity for all Queenslanders to consider ways to make the workplace healthier and safer.

Glenzeil is proud to be working with Mates in Construction – an organisation set up to educate the industry about the high levels of suicide in the construction sector.  The suicide rate for young workers in the Queensland construction industry is more than twice the national average for men. As part of Safe Work Australia Week, Glenzeil will target their safety message towards improving the mental health and wellbeing of all workers.

Brian Gabriel, Director of Glenzeil said Safe Work Australia Week was an important initiative for the construction sector. “Glenzeil is committed to maintaining extremely high standards in workplace health and safety, and as such we are proud to actively support Safe Work Week Australia 2011,”

“Throughout the week we held activities across our sites to engage our staff and sub-contractors in the importance of physical health, mental health and safety at work, and how it is everyone’s responsibility. Mates in Construction addressed Glenzeil staff on site, at the Jupiters Casino project.  We feel this information session was critical to generating awareness about the mental health issues affecting construction workers, particularly now in a slow market”, Mr Gabriel said.

Activities throughout the week included on-site barbeques at Beenleigh Police Station, Robina Health Precinct, Jupiters Casino and at the Head Office. We also attended the Zero Harm at Work Leadership Breakfast and WHS Information Sessions.  Glenzeil’s in-house fundraising campaigns will see all proceeds going to Mates in Construction.

Monday, October 17, 2011

Glenzeil Wins at Master Builders State Awards





Glenzeil wins another award at the Master Builders State Awards on Friday 14th October 2011. QLD State Winner “H20″ at Varsity Lakes - 2011 Best Low-Rise Multi Residential Housing (Townhouses). Congratulations to Matt, Kieran, Joe, Michelle, David, Adam, Henk & Brock.




H2O is compromised of 60 x residential dwellings (44 units + 16 villas) over a, 2300m2 basement plus a Central Facilities area with gym, 25m lap pool, managers office & BBQ area all located in tropical landscaped grounds within a 7,650m2 secure complex. The apartments were broken up into three different buildings, up to 4 stories and servicing by 5 x lifts. H2O had high levels of finishes with sales prices ranging from $550,000.00 to $1,300,000.00.


Tuesday, October 11, 2011

Lismore Gateway Motel - On Site Progress



On-site Progress:

- Site ready for landscaping and pool works.
- Drive way works continuing to the east end of the job.
- Internal lining completed this week.

Monday, October 3, 2011

Code Apartments, Bowen Hills - On Site Progress




Robina Health Precinct - On Site Progress







Level 1
Plasterboard sheeting to Partition walls
Complete Plumbing rough in

Level  2
Structural steel to Partition walls
Services rough in to Partition walls
Complete external Window glazing

Level 3
Complete High level Services rough in
Erect Partition stud walls

Level 4-Roof
Completing substructure framework
Commence Window sub sill installation
Commence Box gutter/Roof sheeting

External Facade work
Substrate structure East / Northern elevations

Stage 2 Car Park
Soft ground Civil works

Sunday, October 2, 2011

Serene on Tweed - On-Site Progress


Serene on Tweed officially started on 5th September 2011 after an early works package completed by the developer. The Subcontractors are currently working to subgrade/ blind and waterproof the basement raft slab. The basement slab will be poured in two parts with the first targeted for 10.10.11. Milestone dates are the crane erection in the first week of November and the completion of the podium slab 18.11.11.