Code Apartments, Bowen Hills - On Site Progress








PROGRESS REPORT: Jeays Street
·         Air conditioning condenser units are installed to mechanical platform.
·         Roof safety systems almost complete.
·         Roof terrace blockwork complete with tiling to commence shortly.
·         Structural steel to gym complete.
·         Pool waterproofing to commence shortly.
·         Installation of driveway off Hurworth Street underway.
·         Hurworth Street scaffold drop nearing completion.
·         Dropping of Jeays Street scaffold is well underway.
PROGRESS REPORT: Finishes
·         Fire sprinkler fit off in basement almost complete.
·         Main switchboard and fire service pump installed.
·         Defecting of units by Xede from ground floor to Level 4 units have commenced.
·         Level 5 carpeting is well advanced.
·         Level 6 joinery nearing completion.
·         Tiling to level 7 almost complete with final fit off in progress.
·         Joinery to level 8 has commenced.
·         Level 9 wall sheeting underway with fire rated ceiling nearing completion.
·         Roof top landscaping has commenced.
KEY DATES:
·         Crane: Will be de-crewed on 19th August 2011 and will be removed on 27th August 2011.
·         Major Scaffold: All scaffold shall be removed by 13th August 2011.
·         Builders Lift: Fully operational.
·         Install Roof: Soffits nearing completion including scaffold drop on Jeays Street and Southern Elevation. Hurworth Street elevation complete except for removal of loading bay scaffold on both ends. This shall be removed on 5th August 2011.
·         Project Handover: 26th October 2011
 