Lismore Gateway Motel - On Site Progress










On Site Progress:

- Internal works, 12 To 15 units sheeted and set ready for painting & tiling Monday 22/8/11.

- External Scaffolding strip starting Monday 22/8/11.

- Lower Restaurant roof sheeting to start Monday 22/08/11.

- All roofing works to be completed by Friday 26/8/11.  