· Clearing of site vegetation nears completion.
· Raking Piling works nearing completion.
· Bulk excavation has commenced.
· Removal of rock and soil is underway.
· Capping beam approximately ¼ complete.
KEY DATES:
· Crane Install – 27th March 2013
· Scaffold Install – 8th June 2013
· Basement 2 Slab Pour – 29th April 2013
· Basement 1 Slab Pour – 14th May 2013
· Ground Level Slab Pour – 27th May 2013
· Hoist Install – 29th June 2013
· Install Lift Roof – 1st November 2013
· Finish Main Roof – 1st November 2013
· Hoist Removal – 21st February 2014
· Scaffold Removal – 31st January 2014
· Crane Remove – 5th February 2014
· Handover – 27th March 2014
· Pour 1 First Level Slab – TBA
· Pour 2 First Level Slab – TBA
· Pour 1 Second Level Slab – TBA
· Pour 2 Second Level Slab – TBA
· Pour 1 Third Level Slab – TBA
· Pour 2 Third Level Slab – TBA
LIST OF SUBCONTRACTORS & SUPPLIERS:
TRADE
|
POSITION
|
Civil Works
|
Delta Group
|
Electrical
|
CV Services Group
|
Fire Sprinklers
|
Select Fire
|
Lifts
|
MP Lifts
|
Mechanical – A/C
|
Climate Control
|
Plumbing
|
Underground Plumbing
|
Surveyor
|
Bennett & Bennett
|
Tower Crane & Hoist
|
Lindores Constructions Logistics
|
SAFETY:
- A site specific Workplace Health and Safety Plan has been produced and is available for inspection.
- There have been 0 No. incidents to date
- No visits to site from Queensland Workplace Health & Safety to date.
GLENZEIL SITE STAFF:
NAME
|
POSITION
|
TELEPHONE
|
Alan Moss
|
Operations Manager
|
5555 3333
|
Andy Ingram
|
Project Manager
|
5555 3333
|
Joel Martin
|
Contracts Administrator
|
5555 3333
|
Jimmy Pearce
|
Project Manager
|
5555 3333
|
Neil Brindley
|
Finishing Foreman
|
5555 3333
|
Sarah Eke
|
Administrators Assistant
|
5555 3333
|
If you have any items you would like us to include in future issues of the newsletter, please contact Sarah Eke
Superb info !! Love it !!! Thanks...Quite a lot of necessary information about crane lift brisbane
ReplyDeleteBuilders cleaning service Gold Coast knows that the Plaza site is situated just behind the Brisbane Convention Centre and close to the South Bank rail station and bus interchange.
ReplyDeleteyour november news later is superb and images that you have use in your post is to good.
ReplyDeletecrane lift brisbane
These articles and blogs are certainly sufficient for me personally for a day.
ReplyDeleteelectricians brisbane