Metrowest Warehouse - On-Site Progress



With the structure now in place, all attention turns to the internal finishes throughout the office & warehouse building. Lockup to the warehouse is imminent with the installation of all windows and roller doors this week. Service rough-in is currently in progress to all 3 levels, getting ready for wall & ceiling sheeting. Over the next month, the critical path tracks the fitout of the office including tiling, carpet and joinery, with a high quality finish expected and externally with the render and paint and commencement of the civil drainage, ready for the carpark and landscape works.

All submitted Extension of Time claims have been approved and Glenzeil currently anticipates completion in late July 2012.