Glenzeil commenced works onsite on the 6th February 2012, with early works comprising of clearing the site vegetation and establishing the warehouse pad.  Interruptions due to ongoing inclement weather has provided difficulties in excavating and finishing ground footings & casting the concrete tilt-up panels onsite.  With the completion of 79 no. bored piers last week, tilt-up erection followed with the warehouse now stood ready for the structural steel which will be ongoing over the next week.  The critical path then moves over to the second part of the construction; the 2 level suspended office which comprises conference rooms, offices, workstations, kitchens and amenities.  