Robina Health Precinct - On Site Progress


On Site Progress:

Car park/Ground Level
  • Chipping /seal coat
  • Landscaping(Soft/Hard)
  • External cladding
  • Sewer/stormwater connection
  • Scaffold dismantle

Levels 1/2/3 (Final Finishes)
  • Hardware  fit off
  • Floor finishes
  • Paint
  • Group 2 items
  • W.C. Partitions
  • Progressive Permanent  power

Level 4
  • Water proofing
  • Ceiling framing
  • Floor/wall tiling
  • (Plant area) Charging A/C lines