Code Apartments, Bowen Hills - On Site Progress




On site progress:

Ground, Level 1 & Level 2:
·         Defected by Xede.

Level 3:
·         Carpet installation in progress.
·         Balcony tiling nearing completion.
·         Final fit off complete.

Level 4:
·         Carpet installation to commence shortly.
·         Balcony tiling and final fit off in progress.

Level 5:
·         Joinery nearing completion.
·         Ready for shower screens and mirrors.

Level 6:
·         Joinery in progress.
·         Internal tiling nearing completion.

Level 7:
·         Joinery to commence shortly.
·         Internal tiling underway.

Level 8:
·         Wall sheeting complete with setting underway.
·         Skirtings and architraves has commenced.

Level 9:
·         Window installation well underway.
·         Wall framing has commenced.

Roof:
·         Roof terrace blockwork complete.
·         Roof terrace roof complete with metal roofing almost complete.
·         Mechanical Platform well underway.
·         Roof Safety System underway.