The Robina Health site is at present on program & is prepping for Level 4 pour 7 on Monday
25.07.11.
Southern End
· Reinforcement steel & stressing is being installed.
· Formwork is being closed up.
Northern End
· Vertical walls are being formed & concrete poured.
· Form work framing out for Level 4pour 8.
Ground / Level 1
· High level services trades are roughing in.
· Block layer is commencing on External / Internal walls.