On site progress:
Ground, Level 1 & Level 2:
· Defected by Xede.
Level 3:
· Carpet installation in progress.
· Balcony tiling nearing completion.
· Final fit off complete.
Level 4:
· Carpet installation to commence shortly.
· Balcony tiling and final fit off in progress.
Level 5:
· Joinery nearing completion.
· Ready for shower screens and mirrors.
Level 6:
· Joinery in progress.
· Internal tiling nearing completion.
Level 7:
· Joinery to commence shortly.
· Internal tiling underway.
Level 8:
· Wall sheeting complete with setting underway.
· Skirtings and architraves has commenced.
Level 9:
· Window installation well underway.
· Wall framing has commenced.
Roof:
· Roof terrace blockwork complete.
· Roof terrace roof complete with metal roofing almost complete.
· Mechanical Platform well underway.
· Roof Safety System underway.