On Site Progress:
- Internal works, 12 To 15 units sheeted and set ready for painting & tiling Monday 22/8/11.
- External Scaffolding strip starting Monday 22/8/11.
- Lower Restaurant roof sheeting to start Monday 22/08/11.
- All roofing works to be completed by Friday 26/8/11.